California Lien Law Summary

Prepared by:
Levy · von Beck & Associates, P.S.
600 University Street, Suite 3300
Seattle, WA 98101 (206) 626-5444
www.levy-law.com

The information contained in this document is an interpretive summary of the private and public works construction lien statutes and is subject to change without notice. Levy · von Beck & Associates, P.S. strongly recommends that the user seek legal counsel before relying on this document to confirm that the information is current and accurate. This document is provided as a courtesy and, as such, Levy · von Beck & Associates, P.S. accepts no liability in connection with reliance thereon or any loss sustained by anyone using or relying on the information contained herein. The intended use of this document is to provide a framework for understanding and dealing with the construction lien statutes.

QUESTIONS

What work is covered?

Who may give a stop notice, file a lien, or make a claim against the bond?

(As of 01/11)

PRIVATE WORKS

[Civil Code (CC) Div. 3, Tit. 15 (Works of Improvement); Business and Professions Code (B&PC) Div. 3, Ch. 9 (Contractors)

All private works of improvement. [CC 3106] NOTE that the work done must be permanent. NOTE ALSO that there must be actual visible work on the land or the delivery of construction materials to the jobsite in order for a mechanics’ lien to attach. An architect, surveyor or engineer may obtain a design professional’s lien, which does not require actual visible work [CC 3081.2], but a contractor cannot currently obtain a design professional’s lien [D’Orsay Int’l Partners v. Superior Ct. of Los Angeles County, 123 Cal.App.4th 836 (Dist.2 2004)]. The removal or demolition of a building need not be part of a larger project leading to something more than the removal or demolition, in order to be a “work of improvement” justifying mechanics’ liens. [CC 3106; United Rentals Northwest, Inc. v. Snider Lumber Products, Inc., 174 Cal.App.4th 1479, 95 Cal.Rptr.3d 471 (Dist.5 2009)]

Stop notice: Licensed contractors -- except the prime contractor, licensed sub- contractors of any tier, and suppliers of labor, services, equipment, or materials to those parties may give a stop notice to either the owner or the lender. The prime contractor may give a stop notice only to the

PUBLIC WORKS

[Civil Code (CC) Div. 3, Tit. 15 (Works of Improvement); Public Contract Code (PCC)]

Any work of improvement contracted for by a public entity. [CC 3100] Accordingly, where a project is on public property leased to a private entity, and the contract is with the private entity and not the public body, there are no “lien” rights against the public entity. [North Bay Const., Inc. v. City of Petaluma, 143 Cal.App.4th 552, 49 Cal.Rptr.3d 455 (Dist.1 2006)]

A payment bond is required on all projects in excess of $25,000. [CC 3247]

NOTE that from now until January 1, 2014, retainage is not to be withheld on a Department of Transportation project. [PCC 7202]

Licensed subcontractors of any tier, suppliers of labor, services, equipment, or materials to at least a subcontractor, fringe benefits trust funds, and contractors who perform “site improvement” work may give a stop notice or make a claim against a payment bond.

lender. [CC 3158-59]

Lien and payment bond: Licensed contractors, licensed subcontractors of any tier, and suppliers of labor, services, equipment, or materials to those parties may file a mechanics’ lien or claim against a bond. [CC 3110-12, 3226] Suppliers to suppliers are NOT entitled to bring any claim. [Tarter, Webster & Johnson, Inc. v. Windsor Developers, Inc., 217 Cal.App.2d Supp. 875, 31 Cal.Rptr. 452 (1963)] Fringe benefit trust funds are also entitled to give stop notices, file mechanics’ liens, and make claims against payment bonds [CC 3111, 3158, 3226], as are contractors who perform “site improvement” work, such as demolition, grading, or excavating [CC 3112, 3158, 3226]. Generally, one who transports materials to a jobsite has no lien rights EXCEPT where (1) the hauler owns the materials and the hauling is part of the cost; (2) the hauler participates in the work of improvement, or (3) the hauler is hired by an agent of the owner. [Ivy Trucking, Inc. v. Creston Brandon Corp., 84 Cal.App.4th 85, 100 Cal.Rptr.2d 582 (Dist.4 2000)] NOTE that where contractors or subcontractors are required to be licensed, they must have the appropriate license in order to bring any action for compensation for work performed or materials provided, and that includes both breach of contract and statutory claims (stop notice, mechanics’ lien, or bond claim). In fact, if a contractor is not licensed, an owner can sue to recover compensation already paid to the contractor. [White v. Cridlebaugh, (178 Cal.App.4th 506, 100 Cal.Rptr.3d 434 (Dist.5 2009)] NOTE ALSO that a contractor who is unlicensed when it entered into the contract, but licensed when the work began will have lien rights, but a contractor that starts the work without a license but obtains a license during the project will not have any lien rights for the project, nor can it bring a breach of contract claim. [B&PC 7031; MW Erectors, Inc. v. Niederhauser Ornamental and Metal Works Co., Inc., 36 Cal.4th 412, 30 Cal.Rptr.3d 755, 115 P.3d 41 (2005); Great West Contractors, Inc. v. WSS Industrial Construction, Inc., 162 Cal.App.4th 581, 76

3248; Union Asphalt, Inc. v. Planet Ins. Co., 27 Cal. Rptr. 2d 371, 21 Cal. App. 4th 1762 (1994)] The prime contractor cannot give a stop notice. [CC 3181] Suppliers to suppliers are not entitled to bring any claim. Generally, one who transports materials to a jobsite has no lien rights EXCEPT where (1) the hauler owns the materials and the hauling is part of the cost; (2) the hauler participates in the work of improvement, or (3) the hauler is hired by an agent of the owner. [Ivy Trucking, Inc. v. Creston Brandon Corp., 84 Cal.App.4th 85, 100 Cal.Rptr.2d 582 (Dist.4 2000)]

Mechanics’ liens are not permitted against public property.

  Cal.Rptr.3d 8 (Dist.2 2008); Banis
  Restaurant Design, Inc. v. Serrano, 134
  Cal.App.4th 1035, 36 Cal.Rptr.3d 532
  (Dist.3 2005)]  
What is the claim Stop notice: Unexpended construction
against? funds. A stop notice may be either bonded
  [CC 3083] or unbonded [CC 3103], and
  operates by requiring the holder of the funds
  to retain funds sufficient to cover the claim.
  NOTE, however, that where a payment
  bond has been recorded, a construction
  lender has the option to require a stop-

notice claimant -- other than a prime contractor who filed a bonded stop notice -- to instead file a claim against the bond. [CC 3159]

When deciding whether to give a stop notice, there are several important considerations. A general contractor may not give a stop notice to an owner, only to a construction lender. If a general contractor gives an unbonded stop notice (not a bonded stop notice) to a lender and if the contractor provided a payment bond on the project, the lender may not be required to withhold funds. Furthermore, where a payment bond has been recorded, a construction lender has the option to require a stop-notice claimant -- other than a prime contractor who filed a bonded stop notice -- to instead file a claim against the bond. [CC 3159] NOTE ALSO that where a bonded stop notice is given, attorney’s fees will be awarded to the prevailing party. [CC 3176]

NOTE that giving a stop notice is not a prerequisite to claiming a lien against the property, unless the owner demands in writing that the claimant serve a stop notice. If the owner so demands, then the claimant who fails to give the stop notice will lose his or her lien rights. [CC 3158] NOTE ALSO that filing a preliminary notice is a prerequisite to filing a stop notice for certain types of claimants. See the section on “Who must give preliminary notice?” below.

Lien: The project itself, the land it is on, and a convenient space surrounding it. [CC 3128] NOTE that where a tenant has contracted for the construction, the owner

Stop notice: Funds to be paid to general contractor. [CC 3186]

Payment bond: The contractor’s payment bond [CC 3249] or the public entity if it fails to ensure that a contractor provides a sufficient bond with a valid insurer, or fails to ensure that the contractor provides a payment bond at all, then the public entity will be liable to unpaid subcontractors. [Electrical Electronic Control, Inc. v. Los Angeles Unified School District, 126 Cal.App.4th 601, 24 Cal.Rptr.3d 316 (Dist.2 2005)]

Retention: Funds withheld from or by the prime contractor. [PCC 7107] NOTE, however, that from now until January 1, 2014, retainage is not to be withheld on a Department of Transportation project. [PCC 7202]

may exempt the property interest from the lien by recording and posting on the project site a “Notice of Nonresponsibility” within 10 days after the owner learns of the work of improvement. [CC 3129, 3094] Such a notice will not, however, protect an owner who participates in the contract to make the improvements or if the lease requires the tenant to make the improvements. [Howard S. Wright Constr. Co. v. Superior Court, 106 Cal.App. 4th 314 (Dist.1 2003)] NOTE ALSO that the claim of a subcontractor or general contractor will be limited, as each is entitled to recover only the amount due to it less all other claims for labor, services, equipment or materials included within his or her contract. [CC 3140]

Payment bond: The payment bond, where the owner, contractor or subcontractor has provided one. [CC 3096]

Other: There are provisions for collecting against the retainage, if any is withheld. [CC §3260] There is also a provision for an owner or tenant to provide security to the general contractor when the project exceeds certain dollar amounts. [CC 3110.5] See the “Other Remedies” section at the end of this summary.

Who must give Stop notice, lien, and payment bond:
preliminary notice? Every claimant, except the prime contractor,
  trust funds, and people performing actual
  labor for wages, must give preliminary
  notice. [CC 3097, 3114, 3160, 3242]
  NOTE that if materials, services, labor, or
  equipment are furnished under more than
  one subcontract, the preliminary notice must
  be given separately with respect to each
  customer. [CC 3097(g)]    
  General contractors: There are specific
  notices required under the Business and
  Professions Code which may be considered
  a type of preliminary notice and that must be
  included by all contractors in contracts with
  owners, although the notices vary by type of
  contract, e.g., commercial, home
  improvement (including swimming pool
  construction), service and repair, etc. See
  Forms F [B&PC 7030(a)] and G [B&PC
  7030(b)]. NOTE that all contractors who

Stop notice: All claimants must give preliminary notice. [3183, 3098] Remember that a general contractor is not a claimant because general contractors cannot give any kind of stop notice on a public project. [CC 3181]

Payment bond: All claimants except trust funds, people who perform actual labor for wages, and a claimant with a direct contract with the general. If a claimant fails to give preliminary notice, a claim against the payment bond can still be made by timely giving the final notice discussed in the sections relating to final notice below. [CC 3252; American Buildings Co. v. Bay Commercial Construction, Inc., 99 Cal.App.4th 1193, 21 Cal.Rptr.2d 539, (Dist.3 2002)] NOTE, however, that it is grounds for disciplinary action against a subcontractor whose contract exceeds $400 to fail to give the required preliminary notice.

have had their license suspended or revoked two or more times within an eight-year period must disclose this to the owner on any residential project of four or fewer units. [B&PC 7030.1] Failure to include required information leaves the contractor subject to disciplinary action [B&PC 7030(c)], and may constitute a misdemeanor [see B&PC 7159.5]. NOTE also that there are numerous other specific requirements, not discussed here, for information that must be included in a home improvement or service and repair contract. [See B&PC 7150-7168]

To whom must Stop notice, lien, and payment bond:
preliminary notice be Generally, claimants must give preliminary
given? notice to the owner or reputed owner, the
  prime contractor or reputed prime
  contractor, and, if there is one, the
  construction lender or reputed construction
  lender. In particular, if the claimant is not
  the prime contractor but contracts directly
  with the owner, the claimant must give
  preliminary notice to the construction
  lender. [CC 3097] NOTE ALSO that a
  subcontractor contracting directly with the
  prime contractor will be excused from
  providing the prime contractor with a copy
  of the preliminary notice [Industrial
  Asphalt, Inc. v. Garrett Corp., 180
  Cal.App.3d 1001, 226 Cal.Rptr. 17 (Dist.2
  1986)], but it is recommended to always
  give the notice to the prime contractor
  anyway. Also, it is no longer required to
  send a preliminary notice to a claimant’s
  subcontractor-customer (if applicable), but
  it is recommended to do so.
  Preliminary notices may be filed with the
  County Recorder, who is then required to
  notify the claimant of the filing of any
  Notice of Completion or Notice of
  Cessation. [CC 3097]  
  General contractors’ specific notices under
  the Business and Professions Code that
  must be included in all contracts with
  owners must be given to the party with
  whom the general contractor is contracting.
  [B&PC 7030-7030.1; see also B&PC 7150-
  7168]    

[CC 3098(b)]

Stop notice and payment bond: Claimants must give preliminary notice to the prime contractor and public agency. [CC 3098, 3252] If the public agency is the Department of Public Works or the Department of General Services, the notice must either be sent to the office of the disbursing officer of the department constructing the work, or be served on the officer personally. It is no longer required to send a preliminary notice to a claimant’s subcontractor-customer (if applicable), but it is recommended to do so. [CC 3098]

Filing a stop notice is not a prerequisite to making a claim against a public works payment bond. [CC 3250]

When must Stop notice and lien: Within 20 days after
preliminary notice be the claimant first furnishes labor, services,
given? equipment, or materials to the job site. If
  given later, the notice will cover only the
  materials, etc. supplied 20 days prior to
  giving notice and thereafter. If notice is
  given by registered or certified mail, service
  is complete at the time it is deposited as
  certified or registered mail. [3097]    
  Payment bond: Same as above.   If,
  however, no preliminary notice is given, the
  claimant may preserve a claim by giving
  final notice to the surety and bond principal
  within 15 days after notice of completion is
  filed, or within 75 days after completion of
  the project, if no notice of completion is
  filed. [CC 3242] NEVERTHELESS, IT IS
  STRONGLY RECOMMENDED that the
  preliminary notice be timely given. And
  because the statute is not specific about
  when a 15- or 75-day notice is deemed
  given, it is recommended that the notice be
  received by the surety and bond principal
  within the applicable time period.    
  General Contractors: The specific notices
  that are required under the Business and
  Professions Code, must be included by all
  contractors in their contracts with owners.
  [B&PC 7030] For home improvements
  including swimming pool construction and
  service and repairs, the contractor must give
  the owner a copy of the contract, signed by
  the contractor and the buyer, prior to starting
  work. [B&PC 7159, 7159.10] [See B&PC
  7030-7030.1; 7150-7168]      
What information Stop notice, lien, and payment bond:   All
must a preliminary of the following:          
notice contain? -General description of labor, materials,
  services, or equipment furnished or to be
  furnished;          
  -An estimate of the total price of labor,
  materials, etc. supplied;      
  -Name and address of claimant;    
  -Name of person who contracted for
  purchase from claimant;      
  -Description of jobsite sufficient for
  identification;          
  -“NOTICE TO PROPERTY OWNER

Stop notice: Within 20 days after the claimant first furnishes labor, services, equipment, or materials to the job site. If given later, the notice will cover only the materials, etc. supplied 20 days prior to giving notice and thereafter. If notice is given by registered or certified mail, service is complete at the time it is deposited as certified or registered mail. [CC 3098] Payment bond: Same as above. If, however, no preliminary notice is given, the claimant may preserve a claim by giving final notice to the surety and bond principal within 15 days after notice of completion is filed, or within 75 days after completion of the project, if no notice of completion is filed. [CC 3252; American Buildings Co. v. Bay Commercial Construction, Inc., 99 Cal.App.4th 1193, 21 Cal.Rptr.2d 539 (Dist.3 2002)] NEVERTHELESS, IT IS STRONGLY RECOMMENDED that the preliminary notice be timely given. And because the statute is not specific about when a 15- or 75-day notice is deemed given, it is recommended that the notice be received within the applicable time period.

Stop notice and payment bond: A substantially accurate general description of the labor, materials, etc. furnished or to be furnished, and the name of the party to whom furnished. [CC 3098]

as set forth in Form A, entirely in bold face type. NOTE that this language must be followed EXACTLY! NOTE that if an invoice for materials includes all the above information -- including the Notice to Property Owner, it will suffice as notice, if given according to the requirements discussed in the following section, “How must preliminary notice be given?”

-If the claimant is a subcontractor who has failed to pay all compensation due to his or her laborers on the job, the notice must also contain the identity and address of any laborer and any express trust fund to which employer payments are due.

NOTE that if an invoice for materials includes all the above information, it will suffice as notice, if given according to the requirements set out here. [CC 3097] General contractors must include in their contracts with owners the notices set forth in Forms F or G, as applicable. [B&PC 7030] And all contractors who have had their license suspended or revoked two or more times within an eight-year period must disclose this to the owner on any residential project of four or fewer units. The notice must be written either in capital letters in 10-point roman boldface type or in contrasting red print in at least 8-point roman boldface type. [B&PC 7030.1] Home improvement contracts including for swimming pool construction have numerous other requirements for information, notices, and warnings, including a “Mechanics’ Lien Warning,” that must be included but are not set out here. [See B&PC 7159-7159.6] Similarly, see B&PC 7159.10-7159.14 for service and repair contracts.

How must preliminary Stop notice, lien, and payment bond:
notice be given? Preliminary notices may be (1) delivered
  personally or by leaving it at the address of
  residence or place of business with
  some person in charge, or (2) sent by
  certified or registered mail to (a) the
  residence or business address, (b) the
  address shown on the building permit; or (c)
  the address shown on any mortgage, deed of
  trust, or other construction loan instrument
  recorded on the project. If notice to a
  person who does not reside in California

Stop notice and payment bond: Preliminary notices must be served on the contractor either (1) by certified or registered mail at any place the contractor maintains an office or conducts business or at his or her residence, or (2) by personal service.

NOTE that where the project is being constructed by the California Department of Public Works or Department of General Services, the notice must also be served on the Department’s disbursing officer either by certified or registered mail to his/her office,

cannot be given by any of those means, then it may be sent certified or registered mail addressed to the construction lender or

prime contractor. [CC 3097(f)]

NOTE THAT PROOF OF SERVICE IS REQUIRED in the form of an affidavit showing the time, place, and manner of service plus the name, address, and, if appropriate, title of person served. If the notice was served by mail, the affidavit must include the return receipt of the certified or registered mail, or a photocopy of the record of delivery and receipt maintained by the post office, showing the date of delivery and to whom delivered, or, in the event of nondelivery, by the returned envelope itself. [CC 3114, 3097.1]

General contractors must give the notices set forth in Forms F or G, as applicable, by including them in their contracts with owners. [B&PC 7030] And all contractors who have had their license suspended or revoked two or more times within an eight-year period must disclose this to the owner on any residential project of four or fewer units. The notice may be given in a bid, estimate, or other document prior to entering into the contract. [B&PC 7030.1] Home improvement and swimming pool contractors must meet numerous requirements in providing information, notices, and warnings. [See B&PC 7159- 7159.6] Similarly, see B&PC 7159.10- 7159.14 for requirements that apply to service and repair contractors.

Who must give final Stop notice: All claimants, except that the
notice? prime contractor cannot give a stop notice to
  the owner (as opposed to the construction
  lender). NOTE that anyone who receives
  from the owner a written demand to file a
  stop notice must do so, or will forfeit the
  right to claim a lien. [CC 3158-59]
  Lien: All claimants. [CC 3110]  
  Payment bond: All claimants who failed
  previously to serve the preliminary notice on
  the surety and bond principal as required for
  a claim against the bond. [CC 3227]
  However, it is recommended that final
  notice be given anyway.  

or by personal service. [CC 3098]

Stop notice: All claimants who are entitled to give a stop notice. The prime contractor who has contracted directly with the owner may not give a stop notice. [CC 3181] Payment bond: All claimants who did not give the preliminary notice. [CC 3252] However, it is recommended that final notice be given anyway.

To whom must final Stop notice: Owner or owner’s architect
notice be given? and construction lender, if any. The notice
  to the construction lender must be given to
  the manager or other responsible officer or
  person AT THE OFFICE OR BRANCH
  HOLDING AND ADMINISTERING THE
  CONSTRUCTION FUNDS. [CC 3083,
  3103]      
  Lien: As of 1/1/11, the lien must be served
  on the owner or reputed owner and then
  filed with the County Recorder where
  property is located together with proof of
  service on the owner or reputed owner. [CC
  3115-3116, 3084]    
  Payment bond: Surety and bond principal.
  [CC 3227]      
When must final notice Stop notice and lien:    
be given? -Prime contractor: After completion of the
  contract and within 60 days after notice of
  completion or cessation is recorded, or
  within 90 days after completion of the
  project if no notice of completion or
  cessation is recorded.    
  -All others: After ceasing to furnish labor,
  materials, etc., and within 30 days after
  notice of completion or cessation is
  recorded, or within 90 days after completion
  of the project if no notice of completion or
  cessation is filed. [CC 3160, 3116]
  To be safe, it is recommended that final
  notice be given within 90 days after the
  claimant’s last delivery to or work on the
  project.      
  BUT if the owner (except the owner-
  occupier of a dwelling with no more than
  four residential units) records a notice of
  completion or notice of cessation and fails
  to timely notify the contractor or other
  claimant who has given a preliminary
  notice, then the deadline for filing the lien is
  extended to 90 days after the notice of
  completion or cessation was recorded. [CC
  3259.5]      
  Payment bond: If no preliminary notice
  was given, then final notice must be given
  within 15 days after notice of completion
  was recorded, or, if no notice of completion
  is filed, within 75 days after completion of
  the project. [CC 3242] However, it is
  recommended that final notice always be
  given regardless of whether the preliminary

Stop notice:

-State job: Director of department that let contract. [CC 3103]

-Any other public job: The controller, auditor, or other disbursing officer for the contract, or the public body that awarded the contract. [CC 3103]

NOTE that in either case it is recommended that final notice be given to the prime contractor as well.

Payment bond: Surety and bond principal. [CC 3252]

Stop notice: Within 30 days after notice of completion/acceptance or cessation is recorded. If no such notice is recorded, then within 90 days after completion or cessation. [CC 3184]

Payment bond: If no preliminary notice was given, then final notice MUST be given to the surety and bond principal within 15 days of the recording of notice of completion or 75 days after completion where no notice of completion is recorded. [CC 3252; American Buildings Co. v. Bay Commercial Construction, Inc., 99 Cal.App.4th 1193 (Dist.3 2002)] It is recommended that final notice be given even if preliminary notice was served.

NOTE that for public works, the date of completion is determined by the date of acceptance by the public body, or where there is a cessation of labor on any public work for a continuous period of 30 days, except as to contracts awarded under the State Contract Act, Chapter 3 (commencing with Section 14250), Part 5, Division 3, Title 2 of the Government Code. [CC 3086]

notice was given.

As to all types of claims: A contract is “complete” for purposes of filing a lien when all work under the contract has been performed, excused, or otherwise discharged. [CC 3160, 3115, 3117; Howard S. Wright Construction Co. v. BBIC Investors, 136 Cal.App.4th 228 (Dist.1 2006)]. Completion of the project” means not only actual completion of the project, but also any of the following: (1) the occupation or use of the improvement by the owner or his agent accompanied by cessation of labor on the project; (2) the acceptance by the owner or his agent of the work of improvement; or (3) a cessation of labor on the project for a continuous period of 60 days, or a cessation of labor for a continuous period of 30 days or more if the owner records a notice of cessation. [CC 3086]

What information Stop notice [CC 3103]:  
must the final notice -General statement of kind of labor,
contain? materials, etc. furnished or to be furnished;
  -Name of person to or for whom furnished;
  -Value of labor, materials, etc. already
  furnished AND of the whole agreed to be
  furnished;      
  -Name and address of claimant.  
  NOTE that the stop notice must be verified
  by the claimant or the claimant’s “agent.”
  Case law does not clarify whether the
  claimant’s attorney is a sufficiently
  authorized agent, particularly if the attorney
  does not have personal knowledge of the
  underlying facts.    
  It is strongly recommended that a written
  request (together with a self-addressed,
  stamped envelope) for notification of the
  owner’s and/or construction lender’s
  election regarding withholding of funds be
  included along with the final stop notice.
  This is because when an owner or
  construction lender receives a stop notice --
  except when a construction lender receives a
  bonded stop notice from the prime
  contractor, the owner and construction
  lender are required to withhold payments
  unless the prime contractor has provided a

Stop notice [CC 3103]:

-General statement of kind of labor, materials, etc. furnished or to be furnished; -Name of person to or for whom furnished; -Value of labor, materials, etc. already furnished AND of the whole agreed to be furnished;

-Name and address of the claimant.

NOTE that the stop notice must be verified by the claimant or the claimant’s “agent.” Case law does not clarify whether the claimant’s attorney is a sufficiently authorized agent.

Payment bond [CC 3227(b)]:

-Kind of labor, materials, etc. furnished; -Name of person to or for whom labor, materials, etc. were furnished; -Amount/value of labor, materials, etc. furnished or to be furnished.

NOTE that the “value” of labor, materials, etc. furnished may also include the 2% penalty for late payment of undisputed progress payments under the Public Contract Code. [PCC 10262.5; Washington Int’l Ins. Co. v. Superior Court, 62 Cal.App.4th 981 (Dist.2 1998)]

payment bond. If the payment bond was given, then they may withhold the funds if they so choose, but they may also elect to require claimants to seek recovery from the payment bond instead. If the OWNER elects not to withhold funds, then within 30 days after receiving the stop notice, the owner must give the claimant details of the

prime contractor’s payment bond. If the CONSTRUCTION LENDER elects not to withhold funds, and the claimant requests notice of the lender’s decision and includes a self-addressed, stamped envelope, then the lender must provide the claimant a copy of the bond. [CC 3161-3162]

Lien [CC 3084]:

-Statement of claimant’s demand less credits and offsets. NOTE that the lien is to be in the amount of the reasonable value of the work and materials furnished or the price agreed upon by the parties, WHICHEVER IS LESS. NOTE ALSO that the lien may include amounts due based on a written modification of the contract or as a result of the rescission, abandonment, or breach of the contract. [CC 3123]

-Name of owner or reputed owner, if known -General statement of the kind of labor, materials, etc. supplied

-Name of person to whom claimant supplied labor, materials, etc.

-Description of the project site sufficient for identification

-As of 1/1/11, the “Notice of Mechanic’s Lien” set forth in CC 3084 (see FORM I), which must be printed in at least 10-point boldface type, with the letters of the last sentence printed in uppercase type, except the Internet Web site address of the Contractors’ State License Board, which is to be printed in lowercase type.

-As of 1/1/11, a proof of service affidavit completed and signed by the person serving the copy of the lien and Notice of Mechanic’s Lien on the owner or reputed owner. The affidavit must show the date, place, and manner of service and facts showing that the service was made in accordance with CC 3084, as well as the name and address of the person or persons upon whom a copy of the mechanics’ lien and the Notice of Mechanic’s Lien was

  served, and, if appropriate, the title or
  capacity in which he or she was served.
  -Verification by the claimant or the
  claimant’s agent. Per case law, verification
  by the claimant’s attorney is sufficient.
  Monarch Metal Weather Strip Co. v.
  Clynick, 117 Cal.App. 270, 3 P.2d 593
  (Dist.1 1931)] See FORM H for the form
  of a notarial acknowledgement.
  FURTHER NOTE that if a claim is against
  two or more structures, with the same owner
  and the same person employing the
  claimant, the claim must designate the
  amount due on each project, or it will be
  enforceable only after all other liens.
  Estimates of the proportionate amounts due
  on the respective portions of the project are
  acceptable. [CC 3130]
  AND NOTE that where the claimant
  performs work or supplies labor to a
  condominium project pursuant to a contract
  with the homeowners’ association, the
  claimant must keep track of the amount
  worked on each unit and segregate it by
  owner in order to enforce a lien for that
  work against the individual homeowners.
  Work performed on, or materials supplied
  to, the common areas must be apportioned
  by shares. Otherwise, the claimant will only
  have a claim against the homeowners’
  association, and not against the individual
  homeowners. [ECC Construction, Inc. v.
  Ganson, 82 Cal.App.4th 572 (Dist.2 2000)]
  Payment bond [CC 3227(b)]:
  -Kind of labor, materials, etc. furnished;
  -Name of person to or for whom labor,
  materials, etc. were furnished;
  -Amount/value of labor, materials, etc.
  furnished or to be furnished.
How must final notice Stop notice: By personal service or by
be given? registered or certified mail (for lender, serve
  on manager or other responsible officer at
  branch administering funds). [CC 3103] To
  ensure that funds are actually withheld,
  personal service is recommended if there is
  any doubt that registered or certified mail
  will not be claimed.
  Lien: By filing with county recorder [CC
  3115-3116] AND, as of 1/1/11, by serving
  by registered mail, certified mail, or first-
  class mail evidenced by a certificate of

Stop notice: By personal service or by registered or certified mail. [CC 3103] Payment bond: By personal service or by registered or certified mail. [CC 3227]

What are the time limits for starting suit?

NOTE that when any contractor or subcontractor files a lawsuit to recover compensation for work performed, he or she must allege that he or she was a duly licensed contractor at all times during the performance of the contract. [B&PC 7031]

mailing, postage prepaid:

-the owner or reputed owner addressed to the owner or reputed owner at the owner’s or reputed owner’s residence or place of business address or at the address shown by the building permit on file with the authority issuing a building permit for the work, or as otherwise provided in CC 3097(j), pertaining to mortgages and other documents; OR if the owner or reputed owner cannot be served by this method, then

-the construction lender or original contractor addressed to the construction lender or to the original contractor. NOTE that service by registered mail, certified mail, or first-class mail evidenced by a certificate of mailing, postage prepaid, is complete at the time of the deposit of that first-class, certified, or registered mail. Failure to serve the mechanics’ lien, including the Notice of Mechanic’s Lien, as prescribed by CC 3084 will cause the mechanics’ lien to be unenforceable as a matter of law. [CC 3084]

Payment bond: By personal service or registered or certified mail. [CC 3227]

Stop notice: More than 10 days after notice is served on either owner or lender AND less than 90 days after the time within which a lien must be filed. [CC 3172] NOTE that this translates into more than 10 days after serving the notice but less than 120 days after the notice of completion or cessation is recorded (150 days for prime contractors), or within 180 days after completion of the work if no notice of completion or cessation is recorded. See “When must final notice be given?” above.

Lien: Within 90 days after claimant records its lien. [CC 3144] NOTE that where a lien was timely recorded but no foreclosure action was filed, and the lien was then released and refiled within the allotted time for filing final notice, the court allowed the claimant to timely foreclose on the second lien. [Koudmani v. Ogle Enterprises, Inc., 47 Cal.App.4th 1650, 55 Cal.Rptr.2d 330 (Dist.4 1996); Coast Central Credit Union v. Superior Court, 209 Cal.App.3d 703 (1989)]

Stop notice: More than 10 days after stop notice served AND within 90 days after the time to file a stop notice expires. [CC 3210] NOTE that this translates into more than 10 days after serving the notice but less than 120 days after the notice of completion/acceptance or cessation is recorded, or within 180 days after completion or cessation of the work if no notice of completion or cessation is filed.) See “When must final notice be given?” above.

Payment bond: After all labor, materials, etc. have been supplied AND within six months after the time to file a stop notice expires. [CC 3249, see 3184]

Retention: After the expiration of the applicable time period(s) within which retention is to be released. Subject to bona fide disputes, retention is to be released by the public entity within 60 days after the date of completion of the improvement, and by the prime contractor within 7 days after the prime receives the funds. If retention is not

  NOTE ALSO that as of 1/1/11, a lis
  pendens must also be filed, either on the
  same day that the suit is filed or within 20
  days thereafter. [CC 3146]   The attorney
  representing the claimant should prepare
  and record the lis pendens.        
  Payment bond: Within 6 months after
  completion of the work of improvement, as
  long as the surety recorded the bond with
  the county recorder before the work was
  completed. [CC 3239-3240]   If the bond
  has not been recorded, the claimant has 4
  years to bring an action against the surety.
  [See CCP 337] However, it is strongly
  recommended that a claimant NOT wait that
  long to bring suit.        
Can attorney fees be Stop notice: Not unless the stop notice is
recovered? bonded, and then only if the claimant is the
  “prevailing party” as determined by the
  court. [CC 3176]        
  Lien and payment bond: There are no
  specific provisions for an award of
  attorney’s fees to claimants. When an
  owner petitions to have property released
  from a lien because no foreclosure suit was
  timely filed, the court is required to award
  attorney’s fees to the prevailing party --
  usually the owner -- up to $2,000. [CC
  3154] NOTE, however, that other causes of
  action under which recovery of attorney’s
  fees may be possible can be joined in the
  same lawsuit with a foreclosure action.
  Attorney’s fees also may be allowed in
  some instances where an arbitrator awards
  them. [Taylor v. Van-Catlin Const., 130
  Cal.App.4th 1061 (Dist.6 2005)] NOTE
  also that in a breach of contract action, an
  owner MAY be able to recover attorney’s
  fees under an attorney’s fee provision in a
  contract between a prime contractor and a
  subcontractor, where the court determines
  that the owner is an intended third-party
  beneficiary of the contract, and the
  contract does not explicitly exclude others
  from the entitlement to fees. [Loduca v.
  Polyzos, 153 Cal.App.4th 334 (Dist.3
  2007)]              
  Retainage: Attorney’s fees   are allowed
  where a claimant must sue to recover
  retention. [CC 3260]        

released as required, it accrues interest at the rate of 2% per month. [PCC 7107] NOTE that the 2% does not compound monthly, and ceases to accrue upon entry of judgment. [S&S Cummins Corp. v. West Bay Builders, Inc., 159 Cal.App.4th 765, 71 Cal.Rptr.3d 828 (Dist.1 2008)]

Stop notice, payment bond, and retention: Yes. [CC 3250 (stop notice), CC 3248 (bond), PCC 7107 (retention)] Attorney’s fees are also allowed to the prevailing party where a subcontractor sues to collect wrongfully withheld progress payments on a project for a public utility. [CC 3262.5]

Are claims assignable? There are no specific statutory provisions
  either allowing or disallowing the
  assignment of claims. However, case law
  shows that liens may be assigned. [See, e.g.,
  Koudmani v. Ogle Enterprises, Inc., 47
  Cal.App.4th 1650 (Dist.4 1996)] CC 3166
  provides that an assignment of construction
  loan funds will not will not affect rights
  under a stop notice.            
How are liens ranked? Stop notice: There are no priorities as
  among valid stop notice claims: funds are
  divided prorata among claimants regardless
  of when the stop notices were served or
  when actions on the stop notices were filed.
  [CC 3167]                
  Lien: Mechanic’s liens are preferred to
  subsequent encumbrances and to prior
  unrecorded encumbrances of which the
  claimant had no notice. [CC 3134]    
Can lien rights be Yes, but only in writing following one of the
waived? statutorily-prescribed forms of waiver   and
  release. A contract cannot require   lien
  rights to be waived. NOTE, HOWEVER,
  that by signing a statutory unconditional
  waiver and release, the subcontractor or
  materialman waives his or her lien rights,
  stop notice rights, and bond rights for all
  services rendered and all materials
  provided up to the date stated on the
  release, even if those services or materials
  were not covered by a payment. It is
  therefore critical that the document signed
  is accurate. NOTE ALSO that   the
  claimant does not waive his or her rights to
  pursue compensation for unpaid services
  and materials under the terms of the
  contract, or to exercise lien rights to
  recover payments for services and goods
  provided after the date specified in the
  release. [CC 3262; Tesco Controls, Inc. v.
  Monterey   Mechanical Co.,   124
  Cal.App.4th 780 (Dist.3 2004)] Forms B -
  E are waiver and release forms that
  conform to the statute (CC 3262).    
Other remedies? Retainage: If retention is withheld, the
  owner must release it within 45 days of
  completion, and the prime contractor must
  do so within 10 days after release by the

Stop notice: There is no specific statutory provision. However, case law shows that stop notice claims may be assigned. [See, e.g., USF&G Co. v. Oak Grove Union School Dist., 205 Cal.App.2d 226 (Dist.1 1962)]

Payment bond: Yes. [See CC 3249]

Stop notice: There are no priorities as among valid stop notice claims: funds are divided prorata among claimants regardless of when the stop notices were served or when actions on the stop notices were filed. [CC 3190]

Payment bond: Funds are divided prorata among those with valid payment bond claims in the same manner as stop notices. [CC 3251]

Yes, although a surety cannot avoid paying a claimant by relying on a waiver given to a

prime contractor, if the waiver document was in error, the claimant did not intend the prime contractor to rely upon it, and the claimant was not actually paid. [See Oldcastle Precast, Inc. v. Lumbermens Mutual Casualty Co., 170 Cal.App.4th 554 (Dist.4 2009)] Contracts with public entities may not include provisions that acceptance of a payment that is otherwise due to the contractor is a waiver, nor may the contract condition payment upon submission of a release of all claims against the public entity. [PCC 7100]

None.

owner. If there is a bona fide dispute between the owner and the prime contractor or the prime and a subcontractor, the owner or prime may withhold up to 150% of the disputed amount. Once the disputed work is complete, the prime or subcontractor should give the owner or prime written notice of its completion. The owner or prime must then notify the prime or subcontractor whether the disputed work is accepted or rejected. If it is accepted, the retention must be released within 10 days. If retention is not timely released, the owner or general must pay 2% interest per month as long as it is withheld improperly. Also, the prevailing party will then be entitled to attorney fees, if an action is filed to recover retention. [CC 3260]

Progress payments: Within 30 days of receiving a written demand for any progress payment, the owner must pay the contractor any undisputed amounts from that payment. If there is a dispute, the owner may withhold 150% of the disputed amount. If funds are wrongfully withheld, the contractor will be entitled to 2% interest per month and its attorney’s fees. [CC 3260.1, 3260]

10-Day stop work notice: If the prime contractor is not paid within 35 days after payment is due pursuant to a written contract and there is no dispute as to the contractor’s performance, then the prime can give a 10-day stop work order to the owner. The prime contractor must notify subcontractors of the stop work order and post notice of it at the job site. The owner must notify the lender. If payment is not received by the prime within 10 days from the date of service of the notice on the owner, then the prime can stop work on the project until the matter is resolved. [CC 3260.2]

Owner’s payment bond: An owner is required to provide a payment bond as security to a prime contractor when the project exceeds $5 million, and a tenant is required to provide a payment bond to the prime contractor when the project exceeds $1 million. The security is not required, however, if the project is construction of a single-family dwelling, or if the owner is a sufficiently large corporation (essentially,

either publicly traded, or privately held with at least $50 million net worth). Only the prime contractor may recover against the security. [CC 3110.5]

No quantum meruit claim: A subcontractor claimant cannot bring a quantum meruit claim against an owner, even if the owner remains indebted to the

prime contractor for the outstanding

amount. [Rogers v. Whitson, 228 Cal.App.2d 662 (Dist.1 1964); Preston Pipelines, Inc. v. JCW-Cypress Home Group, 2006 WL 1119161 (Cal.App. Dist.3 Apr 28, 2006) (Nos. C046055, C047730)]

Special provisions? -If a claimant is employed by the prime contractor or a subcontractor to provide labor, services, equipment, or materials, the claimant’s lien cannot include work or materials not provided for in the owner- prime contract, if the claimant had actual or constructive knowledge of that contract before furnishing the labor, services, equipment, or materials. A claimant will be deemed to have actual notice if the owner- prime contract is filed with the county recorder before commencement of the work. [CC 3124]

-The owner, the prime contractor, a subcontractor, or, in the case of liens, a sub- subcontractor can post a bond for 1-1/2 times the amount of a lien or stop notice and thereby release the lien or avoid the stop notice. [CC 3143, 3171]

-As of 1/1/11, after the complaint to foreclose a lien has been filed, a lis pendens must be recorded to give prospective buyers constructive notice of the claim of lien. [CC 3146]

-Although retainage provisions are not mandatory in public works contracts, they may be included. However, if they are included, provisions apply to allow retention moneys to be invested in securities or placed in an interest-bearing escrow account for the benefit of the prime contractor and, in certain circumstances, subcontractors. [See PCC 10263]

-A subcontractor can include in its claim against the general contractor’s payment bond the 2% penalty imposed by the Public Contract Code for late payment of undisputed progress payments. [Washington International Insurance Co. v. Superior Court, 62 Cal. App.4th 981, 73 Cal.Rptr.2d 282 (Dist.2 1998)]

** Copyright (c) 2010 -- Levy • von Beck & Associates, P.S. **

All rights reserved. No part of this publication may be reproduced or transmitted in any form or by any means without prior written permission of Levy • von Beck & Associates, P.S.

The information contained in this document is an interpretive summary of the private and public works construction lien statutes and is subject to change without notice. Levy • von Beck & Associates, P.S. strongly recommends that the user seek legal counsel before relying on this document to confirm that the information is current and accurate. This document is provided as a courtesy and, as such, Levy • von Beck & Associates, P.S. accepts no liability in connection with reliance thereon or any loss sustained by anyone using or relying on the information contained herein. The intended use of this document is to provide a framework for understanding and dealing with the construction lien statutes.

FORM A

[CC 3097]

(NOTE: This entire Notice must be set out in bold face type, and the language of this Notice must be followed EXACTLY.)

NOTICE TO PROPERTY OWNER

If bills are not paid in full for the labor, services, equipment, or materials furnished or to be furnished, a mechanic's lien leading to the loss, through court foreclosure proceedings, of all or part of your property being so improved may be placed against the property even though you have paid your contractor in full. You may wish to protect yourself against this consequence by (1) requiring your contractor to furnish a signed release by the person or firm giving you this notice before making payment to your contractor, or (2) any other method or device that is appropriate under the circumstances. Other than residential homeowners of dwellings containing fewer than five units, private project owners must notify the original contractor and any lien claimant who has provided the owner with a preliminary 20-day lien notice in accordance with Section 3097 of the Civil Code that a notice of completion or notice of cessation has been recorded within 10 days of its recordation. Notice shall be by registered mail, certified mail, or first-class mail, evidenced by a certificate of mailing. Failure to notify will extend the deadlines to record a lien.

FORM B

[CC 3262]

(For use where the progress payment for which the waiver and release is given has NOT YET BEEN RECEIVED)

CONDITIONAL WAIVER AND RELEASE UPON PROGRESS PAYMENT

Upon receipt by the undersigned of a check from (Maker of Check) in the sum of $(Amount of Check) payable to (Payee or Payees of Check) and when the check has been properly endorsed and has been paid by the bank upon which it is drawn, this document shall become effective to release any mechanic’s lien, stop notice, or bond right the undersigned has on the job of (Owner) located at (Job Description) to the following extent. This release covers a progress payment for labor, services, equipment, or material furnished to (Your Customer) through (Date) only and does not cover any retentions retained before or after the release date; extras furnished before the release date for which payment has not been received; extras or items furnished after the release date. Rights based upon work performed or items furnished under a written change order which has been fully executed by the parties prior to the release date are covered by this release unless specifically reserved by the claimant in this release. This release of any mechanic’s lien, stop notice, or bond right shall not otherwise affect the contract rights, including rights between parties to the contract based upon a rescission, abandonment, or breach of the contract, or the right of the undersigned to recover compensation for furnished labor, services, equipment, or material covered by this release if that furnished labor, services, equipment, or material was not compensated by the progress payment. Before any recipient of this document relies on it, said party should verify evidence of payment to the undersigned.

Dated:

(Company Name)

By:

(Title)

FORM C

[CC 3262]

(For use where the waiver and release is given as part of a contemporaneous exchange for a progress payment or after the payment has been received. NOTE: The NOTICE section at the end of the release must be in print at least as large as the largest type otherwise used in the document.)

UNCONDITIONAL WAIVER AND RELEASE UPON PROGRESS PAYMENT

The undersigned has been paid and has received a progress payment in the sum of $ for labor,

services, equipment, or material furnished to (Your Customer) on the job of (Owner) located at (Job Description) and does hereby release any mechanic’s lien, stop notice, or bond right that the undersigned has on the above referenced job to the following extent. This release covers a progress payment for labor, services, equipment, or materials furnished to (Your Customer) through (Date) only and does not cover any retentions retained before or after the release date; extras furnished before the release date for which payment has not been received; extras or items furnished after the release date. Rights based upon work performed or items furnished under a written change order which has been fully executed by the parties prior to the release date are covered by this release unless specifically reserved by the claimant in this release. This release of any mechanic’s lien, stop notice, or bond right shall not otherwise affect the contract rights, including rights between parties to the contract based upon a rescission, abandonment, or breach of the contract, or the right of the undersigned to recover compensation for furnished labor, services, equipment, or material covered by this release if that furnished labor, services, equipment, or material was not compensated by the progress payment.

Dated:

(Company Name)

By:

(Title)

NOTICE: THIS DOCUMENT WAIVES RIGHTS UNCONDITIONALLY AND STATES THAT YOU HAVE BEEN PAID FOR GIVING UP THOSE RIGHTS. THIS DOCUMENT IS ENFORCEABLE AGAINST YOU IF YOU SIGN IT, EVEN IF YOU HAVE NOT BEEN PAID. IF YOU HAVE NOT BEEN PAID, USE A CONDITIONAL RELEASE FORM.

FORM D

[CC 3262]

(For use where the final payment for which the waiver and release is given has NOT YET BEEN RECEIVED)

CONDITIONAL WAIVER AND RELEASE UPON FINAL PAYMENT

Upon receipt by the undersigned of a check from (Maker of Check) in the sum of $(Amount of Check) payable to (Payee or Payees of Check) and when the check has been properly endorsed and has been paid by the bank upon which it is drawn, this document shall become effective to release any mechanic’s lien, stop notice, or bond right the undersigned has on the job of (Owner) located at (Job Description). This release covers the final payment to the undersigned for all labor, services, equipment, or material furnished on the job, except for disputed claims for additional work in the amount of

$ . Before any recipient of this document relies on it, the party should verify evidence of payment to the undersigned.

Dated:

(Company Name)

By:

(Title)

FORM E

[CC 3262]

(For use where the waiver and release is given as part of a contemporaneous exchange for final payment or after the payment has been received. NOTE: The NOTICE section at the end of the release must be in print at least at least as large as the largest type otherwise used in the document.)

UNCONDITIONAL WAIVER AND RELEASE UPON FINAL PAYMENT

The undersigned has been paid in full for all labor, services, equipment, or material furnished to (Your Customer) on the job of (Owner) located at (Job Description) and does hereby waive and release any right to a mechanic’s lien, stop notice, or any right against a labor and material bond on the job, except for disputed

claims for extra work in the amount of $ .  
Dated:      
          (Company Name)
        By:
          (Title)

NOTICE: THIS DOCUMENT WAIVES RIGHTS UNCONDITIONALLY AND STATES THAT YOU HAVE BEEN PAID FOR GIVING UP THOSE RIGHTS. THIS DOCUMENT IS ENFORCEABLE AGAINST YOU IF YOU SIGN IT, EVEN IF YOU HAVE NOT BEEN PAID. IF YOU HAVE NOT BEEN PAID, USE A CONDITIONAL RELEASE FORM.

FORM F

[B&PC 7030(a)]

(As of January 1, 2006, all licensed contractors except for those writing home improvement contracts or service and repair contracts must include the statement below in at least 10-point type in all written contracts with respect to which the contractor is a prime contractor.)

Contractors are required by law to be licensed and regulated by the Contractors’ State License Board which has jurisdiction to investigate complaints against contractors if a complaint regarding a patent act or omission is filed within four years of the date of the alleged violation. A complaint regarding a latent act or omission pertaining to structural defects must be filed within 10 years of the date of the alleged violation. Any questions concerning a contractor may be referred to the Registrar, Contractors’ State License Board, P.O. Box 26000, Sacramento, CA 95826.

FORM G

[B&PC 7030(b)]

(As of January 1, 2006, contractors must include the following statement in at least 12-point type in all home improvement and service and repair contracts.)

Information about the Contractors’ State License Board (CSLB): CSLB is the state consumer protection agency that licenses and regulates construction contractors.

Contact CSLB for information about the licensed contractor you are considering, including information about disclosable complaints, disciplinary actions and civil judgments that are reported to CSLB.

Use only licensed contractors. If you file a complaint against a licensed contractor within the legal deadline (usually four years), CSLB has authority to investigate the complaint. If you use an unlicensed contractor, CSLB may not be able to help you resolve your complaint. Your only remedy may be in civil court, and you may be liable for damages arising out of any injuries to the unlicensed contractor or the unlicensed contractor’s employees.

For more information:

Visit CSLB’s Web site at www.cslb.ca.gov

Call CSLB at 800-321-CSLB (2752)

Write CSLB at P.O. Box 26000, Sacramento, CA 95826.

FORM H

NOTARIAL ACKNOWLEDGMENT

State of California )
County of )
________________  

On ______________________ before me, [here insert name and title of the officer], personally appeared ______________________________, who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.

I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

WITNESS my hand and official seal.

Signature _______________________________ (Seal)

FORM I

[CC 3084]

(As of January 1, 2011, the notice below must be included in a lien claim.

The following form must be printed in at least 10-point boldface type. The letters of the last sentence must be printed in uppercase type, except for the Web address of the Contractors’ State License Board, which is to be printed in lowercase type.)

NOTICE OF MECHANIC'S LIEN

ATTENTION!

Upon the recording of the enclosed MECHANIC'S LIEN with the county recorder's office of the county where the property is located, your property is subject to the filing of a legal action seeking a court-ordered foreclosure sale of the real property on which the lien has been recorded. That legal action must be filed with the court no later than 90 days after the date the mechanic's lien is recorded.

The party identified in the mechanic's lien may have provided labor or materials for improvements to your property and may not have been paid for these items. You are receiving this notice because it is a required step in filing a mechanic's lien foreclosure action against your property. The foreclosure action will seek a sale of your property in order to pay for unpaid labor, materials, or improvements provided to your property. This may affect your ability to borrow against, refinance, or sell the property until the mechanic's lien is released.

BECAUSE THE LIEN AFFECTS YOUR PROPERTY, YOU MAY WISH TO SPEAK WITH YOUR CONTRACTOR IMMEDIATELY, OR CONTACT AN ATTORNEY, OR FOR MORE INFORMATION ON MECHANIC'S LIENS GO TO THE CONTRACTORS' STATE LICENSE BOARD WEB SITE AT www.cslb.ca.gov.


Construction & Property Loss Claims | Real Estate Litigation | Employment Litigation | General Litigation | Credit & Collection Services | Preliminary Notices & Lien Claim Services
Bellevue | Bellingham | Kirkland | Mercer Island | Olympia | Redmond | Tacoma | Contact | Sitemap | Legal | Outshine Web Design Seattle