Nevada Lien Law Notice Deadlines

Share this valuable resource with your network:

1

Deadline to Give Preliminary Notice

Private:

Within 31 days of first performance and will relate back

Public:

Within 30 days of first performance and will relate back

2

Deadline to File Claim

Private:

Lien: Recorded within the later of 90 days after project completion or 90 days after last performances

Public:

Bond: Within 90 days of last performance; For highway projects, within 30 days of acceptance

3

Deadline to Foreclose

Private:

Lien: Within 6 months of lien filing

Public:

Bond: Within 1 year of last performance; For highway projects, within 6 months of acceptance

4

Common Questions in Nevada

Do Suppliers to Suppliers Have Lien Rights?

0

Is this a full price lien state?

0

The above guidelines are for subcontractors and material suppliers only. General contractors and design professionals may have additional deadlines and should access the Full Summary for notice requirements.

View Sample Summary of Statute »

The Lien Deadline Guides and Lien Law Summaries are provided as a courtesy. Levy • von Beck & Associates, P.S. accepts no liability in connection with reliance thereon or any loss sustained by anyone using or relying on the information contained herein. The Guides and Summaries are designed to provide a framework for understanding and dealing notice requirements and consultation with an attorney is advised.